Hanwa CO., LTD. Responds to a Second Questionnaire from Japanese and Indonesian NGOs Regarding Biomass Fuel Production; Still No Expressing Views on the Impact on Local Residents

Biomass

On May 25, 2026, Hanwa CO., LTD. (Hanwa) provided a response to the questionnaire submitted in January of that year by five Japanese and Indonesian environmental NGOs. In the questionnaire, the NGOs sought the disclosure of environmental impact assessments and the company’s views on the effects of wood pellet production on local residents; however, they were unable to obtain clear answers to many of the questions. As Hanwa produces and imports wood pellets derived from natural forests in Gorontalo Province, Indonesia,  these organizations are calling for a halt to the import of wood pellets from Indonesia to prevent deforestation.

Background Information

In recent years, “Industrial Plantation Forests for Energy (HTE: Hutan Tanaman Energi)”—aimed at producing wood pellets used as a main fuel in biomass power plants in Japan—have been rapidly expanding in Indonesia, covering an area of approximately 1.3 million hectares.
As a result, the logging of natural forests and their conversion into monoculture plantations are proceeding, and local NGOs have reported serious impacts on biodiversity and the lives of local residents, such as increased flood risks and loss of access to forests and farmland.

In particular, wood pellets produced in Gorontalo Province in northern Sulawesi are exported to countries such as Japan and South Korea. In Japan, they are imported by trading companies such as Hanwa.
FoE Japan and four Indonesian environmental NGOs have requested that Hanwa halt imports of wood pellets to prevent further destruction of Indonesia’s natural forests, as well as sent their first letter and questionnaire on November 6, 2025.
Although they received a response from the company on December 11 of that year, they were unable to confirm any clear answers—particularly regarding their views on the environmental impact assessment and the effects on people living near the wood pellet production sites—so they sent a second questionnaire on January 21, 2026.

The table below lists all the questions in a second questionnaire and the responses they received on May 25.

Comparison Table of Questions and Responses

Questions (January 21, 2026)Excerpt from Responses from Hanwa (May 25, 2026)
(1) We understand your position to be that “timber
derived from clear-cutting natural forests and
converting them to gamal plantations”
has the same meaning as “sustainably sourced
timber.” Is this correct?
“We view the reforestation and management of land
where logging or alterations have occurred in the past
as Gamal plantations, in accordance with local laws
and regulations, as a part of our sustainability efforts.”
(2) We also understand that you operate gamal
plantations, but it has nothing to do with the
current sourced raw materials. Is this correct?
“Logging and afforestation / reforestation (in Gamal)
have been conducted in a planned manner aligned
with market trends and its growth conditions based
on applicable laws, regulations and management plans
while leveraging the existing forest resources in the
relevant areas.”
(3) Although you answered that you checked
secondary forests, these forests are still natural
forests. We recognise that clear-cutting and
converting this area to gamal plantations causes
deforestation. Could you please tell us your
opinions based on our recognition?
“~ we recognized that logging and forest alteration
in these areas had already taken place before PT BTL
and PT IGL’ s involvement, that is, prior to the HGU
was granted.”
“We view the reforestation and management of land
where logging or alterations have occurred in the past
as Gamal plantations, in accordance with local laws
and regulations, as a part of our sustainability efforts”
(4) When did you start gamal plantations? 
Do you have any plan to start importing and
selling the gamal as biomass energy?
You already told us it is possible to harvest
for about 4 years. Or is this “Gamal” not being
considered as an imported fuel?
(5)Although you mentioned “We confirm that
PT BJA, PT BTL, and PT IGL are in full compliance
with all applicable laws and regulations”,
could you please let us know specifically about
confirmed laws and regulations?
”~ we comply with applicable laws and regulations
and operate with a strong emphasis on transparency
after obtaining the necessary government permits
and approvals.”
”~ PT PBL and PT IGL supplying raw materials to
PT Biomass Jaya Abadi (PT BJA) as our wood pellet
suppliers are conducting their operations after having
obtained some necessary right to use business lands /
cultivation rights (HGU) from regional office of
Indonesian National Land Agency (BPN) at Gorontalo.”
”We verify compliance with all applicable laws and
regulations related to our business.”
”~ audits, certifications, and on-site surveys
conducted by relevant Indonesian authorities and
independent certification bodies have confirmed that
we comply with all legal requirements, including
those related to land rights, investment, forest
resource utilization, and certification requirements.”
(6) Although you told us “The operations of
PT BTL and PT IGL hold Forest Product Legality
Verification (VLHH) certificates.”, you are not
able to confirm the “sustainability” of raw
materials. Is our understanding correct?
(7) In addition, you also answered “We source
wood pellets only from concession areas where
assessments have been conducted in accordance
with the requirements of Indonesia’s
Environmental Impact Assessment (AMDAL)
system.”, however, there are areas where AMDAL
has not been conducted or is not applicable,
in the concession areas operated by PT. BTL and
PT.IGL. Is our understanding correct?
“~ an Environmental Impact Assessment (EIA/AMDAL)
is conducted appropriately in accordance with
applicable laws and regulations prior to the start of
operations. This assessment has been reviewed and
approved by the environmental authorities with
jurisdiction over the target area, and we have
confirmed that all necessary environmental permits
and approvals have been obtained prior to the start
of operations.”
(8) Is it also correct to understand that PT. BTL and
PT. IGL are conducting logging operations in those
areas, but that these materials are not included in
your company’s procurement?
(9) When is the EIA process implemented?
Which organization approved the EIA?
(10) Regarding step 6 of the EIA process, “Public
Consultation and Approval,” there is no information
provided about “local residents” or “stakeholders.”
Specifically, when and to whom (e.g., officials from
state, prefecture, county, village, or other local
governments) was this consultation conducted?
”~ public consultations are conducted in accordance
with relevant laws and regulations as an important
component of the environmental approval process.
In Indonesia, these procedures involve not only
provincial and regency-level administrative
authorities but also representatives from the
sub-district and village levels.”
(11) The EIA is made publicly available during the
scoping and draft stages, with a period set for
soliciting comments from stakeholders. Did this EIA
follow such steps?
If so, when was the public comment period?
(12) During the comment period from the above
stakeholders, were any information sessions held
for stakeholders?
(13) The five organizations, including the Indonesian
NGO, are interested in the results of the
environmental impact assessment. Is the EIA report
available to stakeholders, including local residents?
Is it possible to share a copy with us?
*Indonesian is perfectly acceptable.
”While the details of the environmental impact
assessment results, including these consultation
records, are not generally made public, dialogue
with stakeholders is a critical element in obtaining
permits and approvals for this large-scale project.”
(14) Are the results of the environmental monitoring
conducted every six months disclosed to
stakeholders, including local residents? Also, would
it be possible to share a copy of the most recent
environmental monitoring results/report with us?
”~ regarding the periodic monitoring and reporting
of environmental impact assessments conducted by
both companies in accordance with Indonesian laws
and regulations, there is a system that allows
stakeholders, including citizens, to participate and
observe the process.”
(15) (the same question as the above)The five
organizations, including the Indonesian NGO, are
interested in the results of the environmental impact
assessment. Is the EIA report available to
stakeholders, including local residents? Is it possible
to share a copy with us?
*Indonesian is perfectly acceptable.
(16) Although you answered “PT BTL and PT IGL
prioritize the principle of Free, Prior, and Informed
Consent (FPIC). ~~~ including those located
downstream of the concession”, could you please
let us know the name of areas and villages?
(17) You also mentioned “We have conducted
stakeholder mapping, participatory mapping,
focus group discussions, and detailed interviews
with relevant key stakeholders in multiple villages,”
when have those activities been done?
Was it conducted as a separate process from the EIA
or as a part of the EIA?
(18) If the Indonesian companies claim to have
gotten FPIC with grassroots communities, is there
a way for us to create documentation based on
community input in order to object to a company’s
logging rights?
If so, could you please let us know about how to do it?
“Procedures and related documents regarding FPIC
(Free, Prior, and Informed Consent), as well as records
of dialogues, opinions, and exchanges with the
community, are prepared and managed by PT BJA,
PT BTL, and PT IGL, and are properly documented as
official records for obtaining permits and approvals.”
(19) We request that your company once again let us
know your perspective on the impacts on the local
community and residents. As our request letter and
reference materials on November 6th, we revealed
that the project has hindered land and forest use and
some residents have rejected the project from the
outset due to concerns about flooding and landslides
caused by deforestation, as well as fears of losing
access to forests essential for their livelihoods as
results of interviews conducted with local residents
by FoE Japan and Indonesian NGOs.
”PT BTL and PT IGL strive to build ongoing
relationships with local communities throughout the
year through various initiatives in healthcare,
education, and socio-cultural activities, while also
actively promoting employment for residents of
Pohuwato District and Gorontalo Province”
 

Related articles

Japanese and Indonesian Environmental NGOs Send a Follow-up Questionnaire to Hanwa Co., Ltd. to Halt Imports of Forest-Destructive Biomass Fuel.

Biomass

Japanese and Indonesian Environmental NGOs Urge Hanwa Co., Ltd. to Halt Imports of Forest-Destructive Biomass Fuel “Indonesia’s forests are not fuel.”

Forests

Related Projects